Western Thermal was the chosen insulation contractor to carry out the insulation to all domestic, heating and chilled water systems. This Phase 1 development consists of a new energy centre, sports hall, café and D9 research and development labs. Exposed to view services within the labs and corridors have been completed with an Aluzinc finish.

Western Thermal also completed the fire stopping to pipework services throughout the building.

Client: Briggs and Forrester
Main Contractor: Contractor: ISG
Project Value: £225,000.00
Programme: November 2015 to June 2016
Location: Malmesbury