Arla Foods Leeds
A new £70 million extension to its flagship dairy in Stourton, Leeds.
This project is the first of its kind which will produce fresh cream, crème, fraiche and will allow it to manufacture cottage cheese for the first time in the UK.
Client: Rotary-Yorkshire
Main Contractor: Caddicks
Project Value: £210'000
Programme: April 2009 through to August 2009




News
Ysbyty Aneurin Bevan
21.07.09
We have been appointed to undertake the insulation work at Ysbyty Aneurin Bevan Hospital.
Bristol Civil Courts
21.07.09
Western Thermal has been appointed to undertake the insulation work at the new Bristol Civil Justice Centre.
Northern Data Centre - Wakefield
21.07.09
Western Thermal has been appointed to undertake the insulation work at the £150million Northern Data Centre Wakefield.
Health & Safety
20.07.09
Three employees of Western Thermal have passed the Construction Skills Safety Courses for supervision.
Ystrad Fawr Hospital
02.04.09
Western Thermal has been appointed to undertake the insulation work at Ystrad Fawr Hospital.